The project objective was to perform a work sampling study and analyze the improvement opportunities by taking the holistic view of the process and identifying the percentage of productive and non-productive activities of pipefitters and welders under study. A work sampling method was chosen as the ideal method to survey the crew, which was used to investigate the proportions of total time devoted to the various work activities taking place. An opportunity to optimize time was uncovered through this method.
The system of pipefitting production is predominately the pipefitting process itself, though there are also additional processes such as hanging pipes in place for continuation of the manufacturing process, as well as set up and cleanup for incoming and outgoing pipes, respectively.
Work stations within the system were experiencing higher than average wait times, either due to tool or machinery requirements or break times by employees. Throughput would experience an increase if these times could be optimized.
In order to identify waste areas and suggest improvement infinitive, it was necessary to obtain the holistic view of the process. Thus, PMC’s project manager conducted several interviews during the onsite visit. Based on the insights obtained during the initial interviews, it was decided to form a crossfunctional team of the key-stakeholders of the material handling process and build the current state value stream map followed by the brainstorming session to identify improvement initiatives aimed at eliminating/reducing current waste in the process.
PMC’s simulation models allowed the company to pinpoint the biggest areas of time spent on nonproductive tasks. This led to several recommendations, such as: